A J Mayr have sucessfully completed the mechanical construction of 600MW Power Plant at the Colongra site near Munmorah on the Central Coast, achieving practical completion sign off on 2nd December 2009.
A J Mayr scope was the mechanical installation of for GT13E2 Gas Turbines and associated balance of plant items.
The Project has had an 14 month duration and the plant was commissioned in September 2009.
Key Challenges
-
As A J Mayr's first Gas Fired Power Plant Construction, we have found the tolerances and technical specifications challenging.
- Maintaining efficiencies and utilisations with a fluid workforce.
-
Maintaining the program with the uncertainty of inclement weather and a site with multiple interfaces.
- Implementation of a Plant and Equipment maintenance program minimising downtimes and ensuring availabilities.
-
Key personnel retention
-
Cash Flow Management
Key Success's
- Experience in mechanical installation works for the power generation industry has been extensive.
-
Combining and utilising our Tomago fabrication shop and yard facilities to assist with criticial path areas of the project.
-
Our key project management personnel have gained key experience
- Equipment utilisation has been strategically planned and executed on a daily basis with the strict confines of the site.
-
A J Mayr has increased its database of skilled resources as a result of this project.
-
A J Mayr has establsihed a strong relationship with the trade unions as a result of their site management at Colongra.
|
Location: Colongra Site Central Coast NSW
Award Date: August 2008
Duration: 14 Months
|
Man Hours: 196073
First Aid Incidents: 22
Medical Treatments: 5
Lost Time Injuries: 0
Near Misses: 46 (inclusive of 9 failed alcohol tests)
|
|
|
|
|
|
|
|