-Colongra Power Station (4 by GT 13E2) 600MW Output
-Sydney Desalination Plant
-Shell Mogas Improvement Project
-Mt Arthur North Project (2)
-Spencer Street Station Redevelopment
-Replacement Research Reactor
-Port Qasim Cold Box Repair
-Mt Arthur North Project (1)
-The Bass Gas Project
-Replacement Research Reactor
Port Qasim Cold Box Repair
Karachi, Pakistan

Specific Project Challenges:
Language barrier, security protection and access to all areas of BOC site. The job in essence was straight forward.

Solution to Overcome Challenges:
BOC organised translator, and security entourage. AJM staff had access passes organised to give them full access to the entire site.

Delivery Method:
Site Job
Project Details
Location: Karachi, Pakistan
Award Date: 10/2003
Duration: 5 Weeks
Safety Statistics
Man Hours: 1,600
First Aid Incidents: 0
Medical Treatments: 0
Lost Time Injuries: 0
Near Misses: 1